Subestação de Marmeleiro – 525KV
CONTRACTOR: TBE
OWNER: TBE
2014 – Santa Vitória do Palmar, Rio Grande do Sul
Execution of electromechanical assembly services, launching and interconnection of cables and assembly of synchronous compensators at the 525 kV Marmeleiro Substation with Synchronous compensator (220MVAr). The work included assembly of all yard equipment for the line input and output bays, launch and interconnection of all power and control cables for yard equipment and control room panels, support for the commissioning necessary for the entire enterprise.